YEAR 1 (Sept 2022 – Aug 2023)

MILESTONES

MS# Milestone Name WP Task Planned Delivery month Delivery date (expected/actual) Status Comments
MS1 Consortium Agreement signed WP1 1.1 1   Achieved Confidential
MS13 Production of a report to define the state of the art in the field (targets for NP) and collect the requests from the community WP2 2.5 3 12 Dec 2022 Achieved MS13 Report
MS2 Preparation of calls for submission of proposals to stable beam access facilities completed WP2 2.1 6 28 Feb 2023 Achieved MS2 Report
MS4 Preparation of the call for submission of projects to access each of the RIs providing radioactive-ion beams WP2 2.2 6 28 Feb 2023 Achieved MS4 Report
MS6 Preparation of the call for submission of projects to access each of the RIs providing neutron beams WP2 2.3 6 28 Feb 2023 Achieved MS6 Report
MS17 RIs ready for TAs WP3 3.2,3.4 6 28 Feb 2023 Achieved MS17 Report
MS19 Work on service improvements started WP3 3.2,3.4 6 28 Feb 2023 Achieved MS19 Report
MS38 Selection of the Training Scientific Board WP5 5.4 6 20 Feb 2023 Achieved MS38 Report
MS37 The source code of the ML toolkit prototype is available on a shared platform WP5 5.3 8 19 Apr 2023 Achieved

Link to the Machine Learning Optimizer toolkit
MS37 Report

MS15 Conceptual plan for online monitoring of long-term operation beam stability WP2 2.5 12 01 Aug 2023 Achieved MS15 Report
MS24 Development and test of the first prototype of the system WP4 4.4.1 12 25 Aug 2023 Achieved MS24 Report
MS28 Upgrade BPM DAQ WP4 4.4.6 12 24 Aug 2023 Achieved MS28 Report
MS32 Design and commissioning of the beam line (vacuum and test chamber) WP4 4.4.9 12 30 Aug 2023 Achieved MS32 Report
MS34 One third of the research infrastructures videos ready WP5 5.1 12 30 Aug 2023 Achieved MS34 Report
MS35 Definition of the catalogue perimeter, architecture, and standards. Release of terms of reference WP5 5.2 12 24 Aug 2023 Achieved MS35 Report


YEAR 2 (Sept 2023 – Aug 2024)

MILESTONES

MS# Milestone Name WP Task Planned Delivery month Delivery date (expected/actual) Status Comments
MS25 Prototype and software ready for lab tests WP4 4.4.3 14 28 Oct 2023 Achieved MS25 Report
MS30 Design of the shielding system including safety related aspects WP4 4.4.7 14 30 Oct 2023 Achieved MS30 Report
MS26 Electrostatic Microprobe Quadrupole Quadruplet Lens Assembly installed and tested WP4 4.4.4 16 19 Dec 2023 Achieved MS26 Report
MS8 Calls for proposals to be hosted at ECT* WP2 2.4 18 22 Jan 2024 Achieved MS8 Report
MS10 Contracted personnel for Theo4Exp VA in place and first codes available for users in the virtual facility WP2 2.4 18 29 Feb 2024 Achieved MS10 Report
MS12 Completed database containing selected features of remote-access toolkit WP2 2.5 18 29 Feb 2024 Achieved

Survey on Remote Access (WP2.5)
MS12 Report

MS14 Reports on FLASH detectors for different facilities WP2 2.5 18 22 Feb 2024 Achieved MS14 Report
MS31 Design of the XY table and purchase of materials and equipment for the device WP4 4.4.8 18 29 Feb 2024 Achieved MS31 Report
MS27 Cooling system developed WP4 4.4.5 18

27 June 2024

Achieved MS27 Report
MS21 a) More than 30% of AU delivered WP4 4.1 24 31 Aug 2024 Achieved MS21 Report
MS22 b) More than 30% of AU delivered WP4 4.2 24 31 Aug 2024 Achieved MS22 Report
MS23 c) More than 30% of AU delivered WP4 4.3 24 31 Aug 2024 Achieved MS23 Report
MS29 ML-based classification and evaluation of the beam profile patterns WP4 4.4.6 24 30 Aug 2024 Achieved MS29 Report
MS33 Mechanics of the setup adapted to fit into the experimental area WP4 4.4.10 24 30 Aug 2024 Achieved MS33 Report


YEAR 3 (Sept 2024 – Aug 2025)

MILESTONES

MS# Milestone Name WP Task Planned Delivery month Delivery date (expected/actual) Status Comments
MS16 Organisation of hands-on workshops & training schools WP2 2.5 30 28 Feb 2025    
MS18 Majority of TAs attributed WP3 3.2,3.4 36 31 Aug 2025    
MS20 Service improvements to RIs implemented WP3 3.2,3.4 36 31 Aug 2025    
MS36 Identification of existing solutions in the EOSC ecosystem and integration of the Nuclear Physics Ecosystem WP5 5.2 36 31 Aug 2025    


YEAR 4 (Sept 2025 – Aug 2026)

MILESTONES

MS# Milestone Name WP Task Planned Delivery month Delivery date (expected/actual) Status Comments
MS9 EURO-LABS-related workshops carried out at ECT* WP2 2.4 42 28 Feb 2026    
MS11 All codes installed at Theo4Exp VA and interoperability among different nodes established WP2 2.4 42 28 Feb 2026    
MS3 All provision of access offered completed WP2 2.1 46 30 Jun 2026    
MS5 a) Completion of all the experiments proposed WP2 2.2 46 30 Jun 2026    
MS7 b) Completion of all the experiments proposed WP2 2.3 46 30 Jun 2026